New construction of a stud farm in the Rosenheim district

Structural Engineering, Timber Construction, Turnkey Construction

The Project

General contractor services – planning & implementation during ongoing operations

The challenging project included cross-trade planning and coordination of all parties involved – all while the horse farm was in operation. This was only possible through close cooperation with the client and the executing companies.

Project scope:
  • Complete planning and coordination of all trades
  • Implementation during ongoing horse farm operations
  • Close coordination with the client and partner companies
Building & area:
  • Four building sections: stable, spa, riding hall, head building
  • 12,000 m² total area, 5,500 m² roof area
Shell & technology:
  • Classic masonry, precast supports, solid foundation
  • Use of 4 cranes and up to 45 shell construction workers
  • Complex special constructions: e.g. 8 m high round walls
  • Special foundation due to sea clay: CSV columns & micropiles
Roof construction:
  • In cooperation with Grossmann Holzleimbau
  • 14 arches, each with a 25 m span
Interior design:
  • High-quality equipment, horse-friendly surfaces
  • Coordination of over 65 subcontractors
  • Up to 85 craftsmen working simultaneously
Project management

Mr. Max Güdemann

Client

Individual

Term

2023 – 2025

Referenz Neubau eines Pferdegestüts Landkreis Rosenheim
Referenz Neubau eines Pferdegestüts Landkreis Rosenheim
Referenz Neubau eines Pferdegestüts Landkreis Rosenheim
Referenz Neubau eines Pferdegestüts Landkreis Rosenheim
Referenz Neubau eines Pferdegestüts Landkreis Rosenheim
Referenz Neubau eines Pferdegestüts Landkreis Rosenheim

Further Insights into our Department

Discover the variety of our construction projects and see our experience for yourself.

Kirchheim Residential Complex
Penzberg Printing Center
Flötzinger Brewery Logistics Hall
Aschheim School Campus
Production building Schaltbau Next Factory
Augustiner Bräu - Filling center Freiham