Flötzinger Brewery Logistics Hall

Structural Engineering, Timber Construction

The Project

Flötzinger Brewery Logistics Hall, Construction Phase 2

September 2023 – October 2024

Storage area 4,800m²

Loading road 1,250m²

Usable area of office wing, ground and upper floor 160m²

Construction:
  • Main supporting structure consisting of 64 precast columns
  • 4,200m² aerated concrete walls, of which 1,400m² with fire wall quality F90, parapet height 10.95m
  • 6,200m² non-reinforced rolled concrete slab with partial concrete core activation
Special features

In a construction period of 12 months, the Flötzinger Brewery’s logistics hall was built in the Schechen industrial area next to the tank farm already presented in 2023 in turnkey construction, in which all four GROSSMANN departments were involved. Under the coordination of the turnkey construction department, the internal coordination of the structural engineering, glued laminated timber construction and asphalt construction trades as well as the technical trades electrical, HVAC (heating, ventilation, sanitary) and 20 other trades took place.

The structural engineering department started the leveling work and precast columns in 2023. Due to weather-related restrictions over the turn of the year, the construction process had to be changed for early use. In just 9 weeks of construction, both the aerated concrete facade and the roof structure – in a complete concept from the glued laminated timber construction department with structural and joinery planning – including temporary sealing were completed by the end of March 2024, so that the gravel leveling and non-reinforced rolled concrete floor slab could be produced as the hall floor in April 2024.

As a result, the hall could be used to a limited extent by the Flötzinger Brewery in May, while the main work on the electrical and rainwater drainage systems as well as the interior finishing of the office wing with lounge area and staff toilets were carried out in parallel.

Only after their completion, the main work on the roof took place over the summer, including roof greening, smoke and heat extraction system (SHEV) and rope safety devices.

In the outdoor area, a total of 3,600m² of asphalt driving surface was installed in the northern and western areas of the hall in May and June 2024, and a semi-rigid asphalt surface cemented in with cement was produced in the southern area on an area of 4,000m², which offers very good resistance to high forklift loads and thus the development of ruts.

When the hall was built, the expansion in the eastern area for a future filling system was already taken into account

Structural engineering site management

Martin Haslberger

Structural engineering foremen

Peter Wallner, Gunter Maurer, Dragan Brukic

Glued laminated timber construction site management

Johannes Koller

Shop drawings glued laminated timber construction

Elisabeth Schmöller

Asphalt construction site management

David Marton, Thomas Amann

Turnkey construction site management

Max Güdemann, Michael Probst

Finishing foreman

Horst Loser

Reference Flötzinger Brewery Logistics Hall
Referenz Flötzinger Brauerei Logisikhalle
Referenz Flötzinger Brauerei Logisikhalle
Referenz Flötzinger Brauerei Logisikhalle
Referenz Flötzinger Brauerei Logisikhalle

Further Insights into our Department

Discover the variety of our construction projects and see our experience for yourself.

Aschheim School Campus
Production building Schaltbau Next Factory
New construction of a stud farm in the Rosenheim district
Augustiner Bräu - Filling center Freiham
Deutscher Alpenverein
Integrated comprehensive school Rinteln