The Project
A multi-story functional building was erected on behalf of the Augustiner Brewery. It includes modern storage areas, a new filling system, technical areas, as well as office and social rooms.
Key data of the new building:
Building dimensions:
- Length: approx. 150 meters
- Width: approx. 37 meters
- Floors: Basement (UG), Ground floor (EG), Upper floor (OG)
Connection & Infrastructure:
- Construction of a connecting structure to the existing logistics hall
- Roofing of the courtyard area for weather-protected loading
- Execution of all work during ongoing logistics operations
Construction:
- Cast-in-place concrete construction with clear heights of up to 6.50 m
- 22 m high and up to 41-ton precast columns
- Ceilings made of precast TT slabs with in-situ concrete
- Facade consisting of a total of 6,000 m² of aerated concrete elements
Scope of execution in a short construction time:
- 5,000 m² roof sealing
- 4,500 m² aerated concrete facade (partial quantity of the total facade)
- 600 m² window areas and mullion-transom facades
Special features of the facade design:
- Supplementing the north facade with a suspended aluminum facade
- High-quality anodizing of the metal facades
- Design elements edged according to a modern barcode grid
Project management
Mr. Max Güdemann
Client
Augustiner-Bräu Wagner KG
Landsberger Str. 31-35
80339 Munich
Term
2022 – 2023